Galliford Try will build the M5 Junction 10 upgrade west of Cheltenham under a £210m contract. The old slip roads shut from early 2027 for about two years.
Galliford Try has won the £210 million contract to build the M5 Junction 10 upgrade west of Cheltenham. Gloucestershire County Council announced the award on Wednesday 25 November.
The construction firm will now take the scheme through its main building phase. It has worked on the design with the council since June 2023, under an Early Contractor Involvement agreement, the council said in its announcement.
The £210 million is the building contract alone. The council expects the whole scheme to cost £372 million.
What the contract covers
The council says Galliford Try will deliver the full set of improvements:
- turning Junction 10 into an all-movements junction, so drivers can join and leave the M5 in every direction for the first time
- a new link road from the A4019 to the B4634 in west Cheltenham
- widening the A4019 Tewkesbury Road
- new walking and cycling facilities
- flood mitigation work
The scheme’s FAQs fill in the detail. Four new slip roads will replace the two that exist today. A new roundabout will sit over the motorway on two new bridges, replacing the current A4019 bridge.
What it means for you
Junction 10 is on the A4019 Tewkesbury Road, about three miles north west of the town centre. It is a half junction: you can join the M5 northbound and leave it southbound, and that is all. Anyone heading south towards Bristol from west Cheltenham has to use another junction.
That changes only once the work is finished, and the disruption comes first. The existing northbound entry and southbound exit slips are due to close from early 2027 for around two years, according to the council’s slip road closures page. The M5 itself stays open. The page still gives no start date and says the length of the closure is under review. We set out the signed diversions for the slip road closures in October.
The last public drop-in session on the closures is today, Thursday 26 November, from 2pm to 7pm at Stoke Orchard Community Centre, about four miles north of Cheltenham. There is no need to book. The project team will have the latest plans and the diversion routes.
When it will be finished
The council’s FAQs give this timetable:
- the main works, including the slip road closures and narrow lanes on the M5, start in early 2027
- the physical works should be complete in spring 2029
- snagging and handover run to spring 2031
Most work will happen between 7am and 7pm, Monday to Saturday, the FAQs say.
Who is paying
The council lists four sources of money for the £372 million scheme:
- the government’s Housing Infrastructure Fund, run by Homes England
- Community Infrastructure Levy money from the district councils
- Gloucestershire County Council itself
- Section 106 payments from developers whose sites benefit directly
The council says the scheme will allow more than 20,000 new homes, over 7,000 of them affordable. It also links it to the Golden Valley development and the National Cyber Innovation Centre, which it says will help create around 12,000 skilled jobs.
Cllr Julian Tooke, the county’s cabinet member for business, economic development, planning and infrastructure, called the award “another significant milestone”. “Once complete, the scheme will make a real difference to how people travel in this part of Gloucestershire, while unlocking new homes, jobs and investment,” he said.
Bill Hocking, chief executive of Galliford Try, said the firm looked forward to “delivering this much-needed improvement scheme that will help unlock economic growth in the region”.
Updates on the scheme, and an email sign-up, are on the council’s M5 Junction 10 page.